We recently had ‘start to finish’ involvement with a local project in East Sussex where the site was initially prepared
with our Proform shuttering system. With use of one of our line pumps and layed with a vibrating tamp, we supplied 32m³ of C40 Powerfloat
mix combined with with Forta Ferro 54 fibers which eliminated the requirement for traditional mesh. The fibers also helped to reduce bleed water.
As a significant consequence, the power floating was completed by 1800hrs despite the situation that it was a cold November day.